Back to implementations

Temporary internal road

TASK

With the expansion of the production facility, there was a need for internal roads for trucks. A solution was sought, the installation of which did not require ground preparation and which would allow temporary passage of vehicles to loading areas.

SOLUTION

It was possible to lay the ROAD SYSTEM road plates directly on the ground because the ground was hard and permeable. Once the surface was levelled, the panels were quickly installed thanks to the special ROAD SYSTEM LINK design.

RESULT

The road was laid in a classic way, by joining the panels along the width of the strip with their longer sides, thus obtaining 3.6 m. The passage of the truck went smoothly with the speed limit of 10 km/h.

USED PRODUCTS
ROAD SYSTEM 200

Check where else you can use ROAD SYSTEM